Moondarra Offtake Pipeline Project

LOCATION

Hazelwood Mine

CLIENT

Lendlease

OUR ROLE

Main Contractor

The Moondarra Offtake Pipeline Project was designed in preparation for the controlled filling of the Hazelwood Mine with water during the rehabilitation process. This pipeline has capacity to deliver up to 28 GL/Yr.


The project included the installation of 2200 meters of DN 900 steel pipe and 150m of DN 900 HDPE pipe discharge system. 


Project delivery works included:


  • Bulk Earthworks to create pipeline easement. 

  • Installation of temporary road diversions.  

  • Detailed excavation works. 

  • In-situ concrete works including strip and pad footings. 

  • 6 detailed road crossings. 

  • 17 Insitu Sliding Stools. 

  • 13 Pipe Guides. 

  • 11 Anchor Blocks. 

  • 134 Pre Cast V-Notch Stools. 


Please contact us if you’d like more information on this or any of our other projects. 

We are an equal opportunity employer.


Foundation Civil & Mining acknowledges Gunaikurnai and Bunurong Peoples as the Traditional Owners of Country across the Gippsland region in which we work. We acknowledge their continuing connection to land, water and community and pay our respect to Elders past and present.  

© 2025 Foundation Civil & Mining

CONTACT US

PO Box 1204

Traralgon VIC 3844

bottom of page